PROJECT DESCRIPTION: Demolition of pool and hardscape. Relocation of portables. Construction of security fencing. Site wide fire alarm upgrades. Installation of audiovisual system at the Commons. |
|
PROJECT UPDATE: Aquatic Center: Temporary sound fencing underway around the Gym. Hardscape demo, sewer and storm drain layout underway. Temp Housing: Building pad has been compacted and certified. Portables have been relocated to new pad. Security Fencing: Temp fencing is set up. Layout underway. Fire Alarm: Conduit runs are being determined along with new panel locations. Commons AV: Conduit runs are being determined. Sheetrock demo to start next week.
PROJECTED SCHEDULE:
Fire Alarm: Construction Start: June 17th, 2024 Completion: August 31st, 2025 Commons AV: Construction Start: June 17th, 2024 Completion: August 31st, 2024 Temp Housing: Construction Start: June 17th, 2024 Completion: August 20th, 2024 Security Fencing: Construction Start: June 17th, 2024 Completion: August 31st, 2024 Aquatic Center Inc. 1: Construction Start: June 17th, 2024 Completion: August 5th, 2025
Tim Ryan, Senior Director of Strategic Facility Planning tryan@srcs.org | (415) 492-3285
Please reach out to Principal Dominguez if you have any questions or concerns regarding construction on campus over the summer!!! jdominguez@srcs.org
|